On Poinsetta Avenue, east of the tennis courts and between Taylor and Pierce, Cape Canaveral has turned a stretch of curb into a construction staging yard. It sits on the block where the city's monthly Friday Fest brings out food trucks, craft vendors and live music. The staging serves the Fillmore Avenue streetscape project, which crews have been building since early August. From now until spring the work moves west, block by block, toward A1A. That puts the November and December festivals, Holiday in the City among them, in the middle of the project.
What is going under Fillmore Avenue
The Fillmore work is listed with the city's other streetscape projects, but most of what it adds will end up underground. The City of Cape Canaveral's capital projects page describes it as part of the Presidential Streets Rehabilitation Plan. It includes stormwater, sanitary sewer and reclaimed water upgrades, plus pervious surfaces and pedestrian improvements meant to help drainage and accessibility. The work runs from State Road A1A east to the beach end.
The stormwater side explains why the project also appears in Brevard County's lagoon reports. The county's Save Our Indian River Lagoon progress reports have tracked it every month this fall. The August 2026 report recorded that construction had begun. By the September report, the project was coordinating delivery of underground stormwater chambers. The October report noted that a video of the Fillmore streetscape had been filmed.
The project took a while to start. Planning began in early 2025, when the city estimated construction for late 2025. Bids were opened in February 2026. City Council asked the two lowest bidders for more information before awarding the contract to Masci General Contractors, Inc. at its April 16 meeting. Engineering alone was listed at $299,900.
The schedule walks west
Crews started at the beach end and are working inland. Here is the city's current timeline:
- Phase one, 400 and 500 blocks: August 3 through December 1, 2026
- Phase two, 300 block: December 2, 2026 through February 10, 2027
- Phase three, 200 block: February 11 through March 5, 2027
- Phase four, 100 block at SR A1A: March 8 through May 11, 2027
- Phase five, all blocks: May 12 through August 2, 2027
The city notes that these dates can shift because of weather, material shortages, labor disruptions or other events outside the contractor's control, and they have moved before. The June 2026 update on the same page gave July 2027 for substantial completion. On the current timeline, the block-by-block work reaches A1A in spring 2027, and a final pass over all blocks runs into early August.
Where the crews meet the festival
Two parking areas have been closed to the public for the length of the project. One is the lot on the east side of the Nancy Hanson Recreation Complex. The other is the parking lot at the Fillmore Avenue beach end. Both are being used for equipment staging, along with the Poinsetta strip east of the tennis courts. The city has said it will post updates on parking as the project goes on.
Friday Fest takes place at Taylor and Poinsetta Avenues. It runs the first Friday of every month except January and July, from 6 to 10 p.m. Admission is free. The city's Friday Fest page asks that pets be leashed and bans bicycles, skateboards and scooters inside the event area. On the city's RecDesk system, the November 6 and December 4 vendor programs are listed at Nancy Hanson Recreation Complex from 5 to 9 p.m. Those times are for vendor registration, so check the public event page before you head out.
The timing is tight in December. Phase one is scheduled to finish December 1, and phase two moves into the 300 block on December 2. Two days later, on December 4, Holiday in the City is held alongside that month's Friday Fest. The city's annual holiday celebration will take place a short walk from a block where crews will have just started digging. With the east Nancy Hanson lot still closed, walking or a quick bike ride makes more sense for anyone who lives nearby. Just leave the bike outside the event area.
The crossing the city named after the festival
The next change is planned for A1A, where the Fillmore work will end. The city is working with FDOT on a pedestrian hybrid beacon between Taylor Avenue and Fillmore Avenue, and its capital projects page explains the purpose.
"This PHB will increase safety while crossing SRA1A for everyday commute, access to beaches, and to get to City Functions such as Friday Fest."
The beacon's letting is scheduled for December 2, 2026. That is the same day Fillmore's phase two begins. FDOT is bundling it with resurfacing of A1A from George King Boulevard to South Carver Drive, which also goes to letting December 2, with construction expected to start in March 2027. If both schedules hold, the Fillmore crews and the A1A resurfacing crews could both reach the highway in spring 2027.
The festival grounds have one fixed point. The Nancy Hanson Recreation Complex will stay as it is for now. The city hired the Lunz firm to design a remodel, put the project out to bid in June 2026, and rejected every bid in August after the costs came in at more than twice the budget. For at least this season, the work on this block is happening in the street and underground, not at the rec center.
A Cape Canaveral December, built around the work
The holiday calendar runs through the phase-two window. All of the dates below fall within it or just before it.
| Date | What | Where |
|---|---|---|
| Friday, November 6 | Friday Fest | Taylor and Poinsetta Avenues |
| Tuesday, December 1 | Fillmore phase one scheduled to finish | 400 and 500 blocks |
| Wednesday, December 2 | Fillmore phase two begins; A1A beacon and resurfacing go to letting | 300 block; SR A1A |
| Friday, December 4 | Friday Fest with Holiday in the City | Taylor and Poinsetta Avenues |
| Friday, December 11 | Reindeer Run packet pickup, 10 a.m. to 6 p.m. | Cape Canaveral Community Center, 7920 Orange Avenue |
| Saturday, December 12 | Reindeer Run 5K, 8 a.m. | Cherie Down Park, 8330 Ridgewood Avenue |
The Reindeer Run starts at Cherie Down Park on Ridgewood Avenue, well north of the Fillmore work. That makes it the one December gathering with no construction nearby. The race page calls it both the 30th and the 31st annual run, so it has been going for about three decades either way.
Before and after, on Astronaut Boulevard
A few Cape Canaveral restaurants on Astronaut Boulevard, the city's stretch of A1A, can bookend a festival night or a race morning.
- Southern Charm Cafe, 8501 Astronaut Blvd, serves from 6:30 a.m. to 2:30 p.m. most days and is closed Tuesdays. It works for breakfast after the Reindeer Run or on a December 2 morning while phase two gets started.
- Thai Thai III, 8660 Astronaut Blvd #108, serves lunch and dinner.
- Zarrella's Italian & Wood Fired Pizza, 8801 Astronaut Blvd, is a sit-down choice for anyone who would rather eat before Friday Fest than at the food trucks.
For more of what's happening north of the Presidential Streets, our summer guide covers the N. Atlantic Avenue circuit. For the port side of town, see living near Port Canaveral.
If you own a home on or near the Presidential Streets and want to know how a rebuilt Fillmore Avenue and a new A1A crossing could affect buyer interest on your block, Megan Ross and The Ross Group follow these projects phase by phase. Schedule a free consultation or start with an instant home valuation, and we'll walk you through what the next six months of work could mean for your street.